- Technical and quality qualification checks that a supplier can make your part to specification, repeatably: a certified quality system, an approved production part, capable processes and a record of how non-conformities are closed.
- Quality certificates are checked against four things: an accredited certification body, a scope that covers the part and process you buy, the site that makes it, and the expiry date.
- PPAP, defined by AIAG, is the evidence package a supplier submits before production: 18 elements, from design records and PFMEA to the control plan, dimensional results, capability studies and the Part Submission Warrant (PSW). Level 3 is the default submission level.
- Traza collects the PPAP package from the supplier by email, checks that it is complete and compares each report with the drawing value by value: part number, revision, tolerances and capability indices against your requirement. It also tracks 8Ds and audit findings to closure and re-checks certificates before they expire.
- The quality engineer reviews what Traza flags and signs off the part. Your auditor visits the site, the certification body issues the certificate and the lab runs the tests; Traza reads their output and keeps it on the supplier's record.
What is technical and quality supplier qualification?
Commercial qualification answers whether you can buy from a supplier: legal entity, tax, sanctions, insurance, bank details. Technical and quality qualification answers whether the supplier can make your part to specification, every time. In a manufacturer that means four things: a certified quality system that covers the site and process, an approved production part (PPAP or first article), capable processes on the characteristics that matter, and a working loop for non-conformities and corrective actions.
ISO 9001 clause 8.4 asks you to set criteria for evaluating, selecting, monitoring and re-evaluating external providers based on their ability to supply conforming product. IATF 16949, AS9100 and ISO 13485 add sector rules on top. The commercial side is covered in the supplier qualification guide for manufacturers; this guide covers the quality side.
How do you check ISO 9001, IATF 16949, AS9100 and ISO 13485 certificates?
A certificate PDF proves little on its own. Check four things on each one: that the certification body is accredited (or, for IATF 16949, recognised by IATF), that the scope covers the product and process you buy, that the site on the certificate is the site that makes your part, and that it is in date. Then confirm it in the public register.
| Standard | Where it applies | What to check |
|---|---|---|
| ISO 9001:2015 | Any manufacturer; clause 8.4 covers control of external providers. | Accredited body, scope, site, expiry. Search the certificate in IAF CertSearch or the certification body's register. |
| IATF 16949:2016 | Automotive production and service parts. Clause 8.4.2.3 expects suppliers to develop their own QMS, with ISO 9001 certification as the minimum. | Issued by an IATF-recognised certification body; site and remote support locations listed; check the IATF certificate database. |
| AS9100D (EN 9100 in Europe) | Aviation, space and defense. Clause 8.4 adds flow-down of requirements and special-process control. | Certificate and audit status in the IAQG OASIS database; scope against the product family. |
| ISO 13485:2016 | Medical devices. Clause 7.4 requires purchasing controls proportionate to the risk of the supplied product. | Accredited body, scope covers the device or component, site, expiry. |
| Special-process approvals (e.g. Nadcap) and lab accreditation (ISO/IEC 17025) | Heat treatment, coating, welding, NDT; labs that issue test reports. | Process and scope listed on the approval; lab accreditation covers the test method used. |
Where do APQP and PPAP fit?
APQP (Advanced Product Quality Planning) is the AIAG framework for developing a new part with a supplier, in five phases: plan and define the program; product design and development; process design and development; product and process validation; and feedback, assessment and corrective action. PPAP is the evidence package at the end of the validation phase: it shows that the production process, run at rate with production tooling, makes parts that meet every requirement. IATF 16949 clause 8.3.4.4 requires a product and manufacturing process approval process; in automotive that is PPAP or the customer's equivalent, such as VDA 2 for German OEMs.
What are the 18 PPAP elements?
The AIAG PPAP manual lists 18 elements. Not every submission needs all of them; the submission level and the customer decide which are sent and which are kept at the supplier.
| # | Element | What it contains |
|---|---|---|
| 1 | Design records | The drawing and specifications at the revision being approved, including material composition. |
| 2 | Authorized engineering change documents | Any change not yet on the drawing, approved by the customer. |
| 3 | Customer engineering approval | Where the customer requires it, e.g. engineering trials. |
| 4 | Design FMEA | If the supplier is design responsible. |
| 5 | Process flow diagram | Every step from receiving to shipping, including rework. |
| 6 | Process FMEA | Failure modes per process step, consistent with the flow diagram. |
| 7 | Control plan | Controls and reaction plans for each characteristic, consistent with the PFMEA. |
| 8 | Measurement system analysis (MSA) | Gauge R&R and other studies for the gauges in the control plan. |
| 9 | Dimensional results | Every characteristic on the drawing, measured, with the result against tolerance. |
| 10 | Records of material and performance test results | Material, chemical, physical and functional tests the drawing or specification calls for. |
| 11 | Initial process studies | Capability (Ppk, Cpk) for special characteristics. |
| 12 | Qualified laboratory documentation | Scope and accreditation of the lab that ran the tests, e.g. ISO/IEC 17025. |
| 13 | Appearance approval report (AAR) | For parts with appearance requirements: color, grain, gloss. |
| 14 | Sample production parts | Parts from the production run used for the submission. |
| 15 | Master sample | A sample kept by the supplier, signed off with the customer. |
| 16 | Checking aids | Fixtures and gauges specific to the part, with their calibration. |
| 17 | Customer-specific requirements | Records of compliance with the customer's own requirements. |
| 18 | Part Submission Warrant (PSW) | The summary declaration, signed by the supplier, approved by the customer. |
What are the PPAP submission levels?
The level says what the supplier sends and what it keeps available for review. At every level the supplier holds the full set of records.
| Level | What is submitted |
|---|---|
| Level 1 | PSW only (and AAR for appearance items) submitted to the customer. |
| Level 2 | PSW with product samples and limited supporting data. |
| Level 3 | PSW with product samples and complete supporting data. The default unless the customer says otherwise. |
| Level 4 | PSW and other requirements as defined by the customer. |
| Level 5 | PSW with product samples and complete supporting data, reviewed at the supplier's manufacturing location. |
How do you review a PPAP package against the drawing?
The review is a comparison: every report against the drawing, the specification and your customer-specific requirements. Much of the effort goes on finding the values, not on judging them.
Check the package is complete for the level requested
List what the level and your customer-specific requirements call for and check each element is there, legible and for this part. A missing MSA or a PFMEA copied from a sister part are typical reasons a PPAP comes back.
Check identity and revision on every document
Part number, drawing revision and engineering change level must match across the PSW, the dimensional report, the control plan and the test reports. A report against revision B in a revision C submission is a rejection, however good the numbers are.
Compare each dimensional result with the drawing
Every characteristic on the drawing should appear in the dimensional results, ballooned, with nominal, tolerance and measured value. Check the reported nominal and tolerance against the drawing, not just the pass or fail column.
Check capability against your requirement
For special characteristics, compare Ppk or Cpk with the value your customer-specific requirements set, or with the AIAG default if you have none. Check the study used enough parts and a measurement system that passed MSA.
Check material and test reports against the specification
Material grade, chemistry and mechanical properties against the drawing's material callout; test methods and lab scope against the specification. Material certificates should carry heat or lot numbers you can trace to the parts submitted.
Check consistency between PFMEA, control plan and flow diagram
Every process step in the flow diagram should appear in the PFMEA, and every high-risk failure mode should have a control in the control plan with a reaction plan.
The quality engineer decides
Approve, approve on an interim basis with a deviation and an action plan, or reject. The decision, the reason and the documents go on the supplier's record.
This is what a value-by-value check looks like. Illustrative example with sample data, not a customer record.
| Item | Drawing or requirement | Reported in PPAP | Result |
|---|---|---|---|
| Part number / revision | 4471-220 rev C | 4471-220 rev C | Match |
| Ø bore, char. 12 | 12.00 ±0.02 mm | 12.03 mm | Out of tolerance |
| Flatness, char. 18 | 0.05 mm | 0.03 mm | In tolerance |
| Ppk, char. 12 (special characteristic) | ≥ 1.67 (customer requirement) | 1.21 | Below requirement |
| Material | EN AW-6082 T6 | EN AW-6082 T6, 3.1 certificate, heat 22-0917 | Match |
What about first article inspection and material certificates?
Outside automotive, the same evidence often comes as a first article inspection report. In aerospace, AS9102 defines it in three forms: part number accountability, product accountability (materials, special processes, functional tests) and characteristic accountability (every design characteristic with its result). A first article is repeated after a change in design, process, site or tooling.
Material certificates and lab results are checked against the drawing and the material specification: grade, chemistry, mechanical properties, heat treatment condition, and the type of inspection document required, such as an EN 10204 3.1 certificate. The heat or lot number on the certificate should trace to the parts delivered, and the lab that issued the results should be accredited for the method used.
How do you manage non-conformities and 8D reports?
When a supplier ships non-conforming parts, you open a non-conformity, contain the stock and ask for a corrective action, usually as an 8D report. The 8D only works if each step is checked, not just received:
- D0: plan the response and decide whether an 8D is needed.
- D1: form the team with the people who know the process.
- D2: describe the problem: what, where, when, how many, how detected.
- D3: contain it: stock at your site, in transit and at the supplier is sorted or quarantined.
- D4: find and verify the root cause, both why it occurred and why it was not detected.
- D5: choose permanent corrective actions and verify they work.
- D6: implement them and validate the result over time.
- D7: prevent recurrence: update the PFMEA, the control plan and the work instructions, and apply the fix to similar parts and processes.
- D8: close the 8D and recognise the team.
The common failure is an 8D that stops at D3 or names a root cause like "operator error" with no verification. Track each open 8D by date, check that D4 explains both occurrence and escape, and check at D7 that the PFMEA and control plan were actually updated. Open and late 8Ds belong in the supplier's quality score.
How do you prepare supplier audits and follow up the action plan?
Before an on-site process or system audit, the auditor needs the supplier's file in one place: certificates and scope, the last audit report and its open findings, PPAP status by part, open non-conformities and 8Ds, and delivery and rejection history. After the audit, each finding becomes an action with an owner, a due date and the evidence that closes it. Findings stay open until the evidence is reviewed, not until the supplier says they are done.
Re-qualification runs on the same record: certificates re-checked before expiry, PPAP resubmitted on changes, audits scheduled by risk. How the quality record combines with financial, sanctions and ESG data is covered in the guide to supplier risk monitoring.
What does Traza do in quality qualification, and who signs off?
Traza is a source-to-pay suite run by AI agents. It runs as your suite and system of record, or on top of the SAP, Ariba, Coupa or Oracle you keep. In supplier qualification, Nora covers the quality side as well as the commercial one:
- Certificates: reads ISO 9001, IATF 16949, AS9100 and ISO 13485 certificates for certification body, accreditation, scope, site and expiry, and asks the supplier for the renewal before it lapses.
- PPAP: emails the supplier the list of elements for the level you request, follows up on what is missing, checks the package is complete and compares each report with the drawing value by value: part number, revision, tolerances, material and capability indices against your requirement.
- First article and material certificates: reads the report and the certificates against the drawing and the material specification, including heat or lot traceability.
- Non-conformities and 8Ds: keeps each 8D open by discipline, chases the supplier by email for overdue steps and checks that the root cause and the PFMEA and control plan updates are there before closure.
- Audits: prepares the supplier's file for the auditor, reads the audit report and tracks every finding and action to closure with its evidence.
Suppliers work by email, with no portal and no account. Your quality engineer gets one review in Microsoft Teams or Slack with what passed, what is out of tolerance or missing, and the source of each value. The checkpoints stay with people: the quality engineer reviews the flags and signs off the PSW; your auditor visits the site; the certification body issues the certificate; the lab runs the tests. Traza reads their output, keeps it on the supplier's record and writes the approval to your ERP only after the engineer signs.
To see the PPAP check on one of your own parts, book a call.
Frequently asked questions
What is the difference between supplier qualification and PPAP?
Supplier qualification approves the supplier: legal and tax checks, sanctions, quality system certificates and risk. PPAP approves a specific part made by that supplier at a specific site and revision. A qualified supplier still needs an approved PPAP for each new part, each engineering change and each relevant process change.
What are the 18 elements of PPAP?
Design records; authorized engineering change documents; customer engineering approval; design FMEA; process flow diagram; process FMEA; control plan; measurement system analysis; dimensional results; records of material and performance test results; initial process studies; qualified laboratory documentation; appearance approval report; sample production parts; master sample; checking aids; customer-specific requirements; and the Part Submission Warrant.
What Ppk does PPAP require?
AIAG's PPAP manual (4th edition) treats an index above 1.67 as meeting acceptance criteria, between 1.33 and 1.67 as possibly acceptable after review with the customer, and below 1.33 as not meeting acceptance criteria, unless the customer sets other values. Many customer-specific requirements set their own values, and those take precedence.
When does a supplier have to resubmit a PPAP?
For a new part, an engineering change, and process changes such as new tooling, a new or moved site, a change of sub-supplier or material, or tooling inactive for a long period. The PPAP manual and the customer's own requirements list the triggers and say when the customer must be notified first.
Can a supplier qualification platform approve a PPAP?
The approval belongs to the customer's quality engineer, who signs off the PSW. Software can collect the package, check it is complete, compare every report with the drawing and specification, and present the deviations, so the engineer reviews the exceptions instead of re-reading every page.
How does Traza handle quality certificates that expire?
Traza keeps the expiry date, scope and site of each certificate on the supplier's record, asks the supplier by email for the renewed certificate before it expires, and checks the new one against the same criteria. If it lapses, or the scope or site changes, the quality team is alerted in Microsoft Teams or Slack and decides what happens to open orders.
Keep reading
Supplier qualification
Supplier qualification for manufacturers: process, documents, risk scoring and audit trail
Supplier qualification
Supplier risk monitoring: external risk intelligence and continuous monitoring for manufacturers
Supplier qualification
How to apply supplier qualification policies to the documents suppliers send
Sources
- AIAG: Production Part Approval Process (PPAP), 4th edition
- AIAG: Advanced Product Quality Planning (APQP) and Control Plan
- AIAG: Quality core tools (APQP, Control Plan, PPAP, AIAG & VDA FMEA, MSA, SPC)
- IATF Global Oversight: IATF 16949 and certification rules
- ISO 9001:2015, clause 8.4: Control of externally provided processes, products and services
- ISO 13485:2016, Medical devices: quality management systems
- SAE AS9100D: Quality management systems for aviation, space and defense organizations
- SAE AS9102C: Aerospace first article inspection requirement
- IAF CertSearch: accredited management system certificates
This article is for information and is not legal advice. Practices and references are for the United States; check what applies to your contracts and your state.